SOUTHERN REGION
WESTERN PROVINCE (16× LLGs)
. 14× LLGs have deployed census units and enumeration in progress.
. 2x LLGs (Nomad Rural and Olsobip Rural), part of the census units deployed. The final units awaiting deployment.
GULF PROVINCE (10x LLGs)
. 2x LLGs (Central Kerema and Kerema Urban) have completed enumeration. Pending quality checks and uploads.
. 8x LLGs have not commenced Tier 3 training. Deployment of census units are pending.
CENTRAL PROVINCE (16x LLGs)
. 16x LLGs census units have been deployed and enumeration in progress. Counting in progress.
NCD (3x LLGs)
. 3x LLGs have commenced enumerations.
. Outstanding allowances have been processed and will be sorted this week.
MILNE BAY PROVINCE (16x LLGs)
. 15x LLGs are pending deployment of census units pending administrative delays on fuel payments.
. 1x LLG (Alotau Urban) had completed counting and started data uploads.
NORTHERN PROVINCE (9x LLGs)
. 5x LLGs have commenced enumeration. Counting in progress.
. 4x LLGs awaiting Tier 3 training and deployment of census units. Payments are in progress for deployment.
ISLANDS REGION
MANUS PROVINCE (12x LLGs)
. 12x LLGs have completed enumeration.
. 11x LLGs completed data uploads.
. 1x LLG (Aua Wuvulu Rural LLG) is yet to upload data. Quality checks are underway, and upload to commence on the 15th July.
NEW IRELAND PROVINCE (10x LLGs)
. 10x LLGs have completed enumeration.
. 5x LLGs have completed data uploads.
. 5x LLGs undergoing quality checks prior to upload of data.
. Census should be completed this week.
EAST NEW BRITAIN PROVINCE (18x LLGs)
. 18x LLGs have completed enumeration.
. Post enumeration quality checks been undertaken.
. Census should be completed this week.
WEST NEW BRITAIN PROVINCE (12x LLGs)
. 10x LLG have completed enumeration and data uploads.
. 1x LLG is doing quality checks and data upload pended for this week.
. 1x LLG still progressing with enumeration.
ARoB (12x LLGs)
. 1x LLG had completed enumeration and data uploaded.
. 11x LLGs still progressing enumeration
MOMASE REGION
MOROBE PROVINCE (33x LLGs)
. 1x LLG (Buang LLG) had completed enumeration and data uploaded. Census completed.
. 12x LLGs still progressing enumeration.
. 14x LLGs undergoing Tier 3 training.
. 6x LLGs pending deployment, tier 3 training (chopper required).
MADANG PROVINCE (19x LLGs)
. 11x LLGs have commenced enumeration.
. 8x LLGs pending deployment, tier 3 training (chopper required).
EAST SEPIK PROVINCE (28x LLGs)
. 27x LLGs have commenced enumeration.
. 1x LLG requires deployment (chopper required).
WEST SEPIK PROVINCE (18x LLGs)
. 3x LLGs have commenced tier 3 training.
. 15x LLGs have yet to commence.
. WE HAVE CONCERN WITH THIS PROVINCE.
HIGHLANDS REGION
HELA PROVINCE (14x LLGs)
. 14x LLGs have all commenced enumerations.
. Thou enumeration have commenced for Hulia LLG, Mount Sisa LLG, Tagali LLG and Tebi LLG, census units have raised security-related concerns for these areas.
SOUTHERN HIGHLANDS PROVINCE (20x LLGs)
. 18x LLGs yet to commence enumeration.
. 2x LLGs commenced enumeration however stopped due to no allowances.
. Enumeration is on stand-still at this point in time.
ENGA PROVINCE (17x LLGs)
. 10x LLGs have commenced Tier 3 training.
. 7x LLGs have not started tier 3 training (chopper required).
WESTERN HIGHLANDS PROVINCE (11x LLGs)
. 5x LLGs have commenced enumeration.
. 6x LLGs have not commenced with Enumeration. Awaiting allowances.
JIWAKA PROVINCE (8x LLGs)
. 5x LLGs have completed tier 3 training. Enumeration to commence on 15th July.
. 3x LLGs have not started tier 3 training.
CHIMBU PROVINCE (20x LLGs)
. 19x LLGs have completed Tier 3 training. Enumeration to commence soon.
. 1x LLG has not done the Tier 3 training.
EASTERN HIGHLANDS PROVINCE (24x LLGs)
. 24x LLGs have commenced enumeration.