PNG Power Limited (PPL), Dirio Gas Power Station and NiuPower Gas Power Station have agreed to work together to increase electricity supply to the Port Moresby Grid amid ongoing power shortages and load shedding.
The agreement follows a meeting between PPL Acting Chief Executive Officer Noel Mobiha and his team, Dirio Chief Executive Officer James Nelson, and NiuPower Chief Executive Officer Michael Uiari.
The discussions focused on identifying short-term solutions to increase power generation and ease the pressure on the Port Moresby Grid while PPL continues to pursue long-term solutions.
Declining Water Levels Affect Hydro Power Generation
The prolonged dry weather associated with the El Niño weather pattern has significantly reduced hydroelectricity generation for Port Moresby.
Water levels at Sirinumu Dam continue to decline, affecting generation at PPL’s Rouna Cascading Power Stations, which include Rouna 1, 2, 3 and 4. Water levels at the Edevu Hydro Dam have also dropped.
With reduced hydro generation, electricity supply to the Port Moresby Grid has fallen below demand, resulting in the load shedding currently experienced by customers.
Dirio’s Third Gas Turbine Could Add 15 MW
One of the key options discussed at the meeting is bringing Dirio’s third gas turbine (GT3), with a generation capacity of 15 megawatts (MW), online.
Dirio has three gas turbines with a combined generation capacity of approximately 45 MW. However, its existing 66kV transmission line can only accommodate about 30 MW, meaning only two turbines can operate at full capacity at a time.
Under the proposed arrangement, Dirio’s third gas turbine would connect through NiuPower and export electricity using NiuPower’s existing 66kV transmission line. Dirio’s other two turbines would continue supplying electricity through its existing transmission line.
Management from both Dirio and NiuPower agreed to work with PPL to explore this arrangement, allowing technical and operational teams from all three organisations to begin assessing the connection and operational requirements.
PPL’s National System Operations team has already conducted preliminary technical studies on the proposed configuration.
Technical Teams to Progress the Arrangement
PPL Acting CEO Noel Mobiha thanked Dirio and NiuPower for their cooperation and support during the current power supply challenges.
“We thank Mr Nelson, Mr Uiari and their teams for standing with PPL during this challenging time,” Mr Mobiha said.
He said the agreement would allow the technical teams to further investigate the proposed configuration.
“Once the connection details are confirmed, the 15 MW from Dirio’s third gas turbine would add power to the Port Moresby Grid and help reduce load shedding. In the meantime, we are continuing our work on long-term solutions,” he said.
PPL thanked its customers for their patience and understanding, assuring the public that updates would be provided as work progresses.
Customers are encouraged to follow PNG Power Limited’s official Facebook page or visit its website for the latest load shedding updates.